Alexander Associates

Alexander Associates

Berkeley is increasing building work by up to 50% over the next six years.

The housing giant is also looking to increase pre-tax profits to a total of £3.3bn over the six years to 30 April 2025 with targeted annual profits of between £500m and £700m.

The move will see the cash rich company hand out £1bn in special dividends to shareholders over the next two years – an increase of £455m on previous plans.

The firm said: “Since the end of the financial crisis in 2011, Berkeley has acquired a number of long-term regeneration sites, a number of which are now in, or coming into, production.

“In total, Berkeley is in the process of bringing forward 25 large and complex residential-led developments, of which 20 have been acquired since the start of this period.

“The execution of this strategy will see Berkeley increase its annual housing delivery (including in its joint ventures) by as much as 50% over the next six years.”

Hinkley Point bulk M&E to start in October

Plans are underway to start the bulk mechanical, electrical, heating and ventilating work on the key Hinkley Point C nuclear island site in the Autumn.

 

The Office of Nuclear Regulation will need to give clearance for the start of the critical work package, after deeming the major milestone a safety-critical stage in the project.

The release of the first bulk MEH hold point by the regulator is expected before on-site work is programmed to start around October this year.

This would be two years since permission for first Nuclear Island concrete was given.

At this point, civil construction work on Unit 1 nuclear island will have reached the point where several individual rooms are structurally complete and ready to hand over from the main civil contractor to the MEH teams.

Balfour Beatty, NG Bailey, Altrad, Cavendish Nuclear and Doosan Babcock are all linked up in the MEH alliance to co-ordinate delivery of the complex installation of cabling and pipework.

Once started, the first bulk MEH installation across both reactor units will take place over a period of around three years, although detailed MEH system completions will continue well beyond that.

The MEH programme involves electrical and mechanical installations encompassing around 4,000 rooms, employing 3,500 workers.

Works will involve 380km of pipework, 20,000 valves, with thousands of welds and associated radiography, and 9000 km of cabling.

HS2 ‘go/ no-go decision’ expected next month

 

HS2 ‘go/ no-go decision’ expected next month

14 JAN, 2020 BY 

 

The government is set to make a final “go/ no-go decision” on High Speed 2 (HS2) in early February, New Civil Engineer has learned.

It is understood that prime minister Boris Johnson will make a final decision on the project at the same time that the government-ordered Oakervee review is made public.

It had previously been suggested that the Oakervee report would be made public ahead of a final decision from government.

However, sources within the rail industry have told New Civil Engineer that Johnson is keen to detail the project’s future as quickly as possible.

“Once the Brexit deadline [January 31] is out the way, the government is keen to move the agenda on quickly,” one rail professional said. “HS2 is front of the queue of things to clear and to clear quickly."

“A decision on whether to proceed or how to proceed is now extremely likely to come at the same time that the report is made public.”

Doug Oakervee submitted his overarching review to the Department for Transport (DfT) in November where it was placed “in a vault” until after the General Election.

Transport secretary Grant Shapps had previously pledged to make the report public “as soon as [he] had it”. However, election campaign rules – and the need to “get Brexit done” – have so far prevented him from doing so.

Speaking in Leeds last week, Shapps confirmed that the report would be published in the “coming weeks”.

The Oakervee review was established to examine the entire HS2 project and make recommendations on the route, specification and project governance.

A leaked draft report published by the Times revealed that Oakervee is set to recommend proceeding with the project in full. However, the draft report did question HS2 Ltd’s procurement process and suggests that some contracts should be retendered.

Last week, former deputy chair of the HS2 review group Lord Berkeley described High Speed 2 (HS2) as a “wrong and expensive solution” and questioned the competence of government officials.

Berkeley, who stepped down from the group on 31 October last year, made the statements in a self-published “dissenting report” on the project, which has been welcomed by environmental campaigners but which has drawn criticism from the rail industry.

Berkeley claimed that review chairman Doug Oakervee’s report has a bias towards accepting HS2 Ltd’s evidence in preference to those of others, leading to a supportive recommendation for HS2 to continue.

He also criticised the involvement – and lack of scrutiny – of Treasury and DfT officials in the review and suggested that costs could be cut by up to £20bn by reducing the “unnecessarily high specification”.

However, HS2 officials have hit back, with former HS2 technical director Andrew McNaughton claiming that Berkeley’s report is “completely and factually wrong”.

Speaking to New Civil Engineer, McNaughton – who still acts as an advisor to HS2 Ltd – contested Berkeley’s conclusions that the project is designed to “an unnecessarily high” specification, that costs could be brought down by lowering the speed and that running 18 trains per hour is “unachievable”.

Yorkshire Water awards £650m infrastructure frameworks

Yorkshire Water has awarded clean and waste infrastructure and customer focused infrastructure frameworks with a combined value of £650 million.

 

The £400m Infrastructure Networks framework covers the delivery of infrastructure pipeline projects for both clean and wastewater assets. The £250m customer focused infrastructure works framework involves the delivery of programmes of work including internal flooding, lead replacement and minor works packages.

Nine partners have been appointed, with these frameworks completing the 12-month AMP7 procurement process following the recent announcements of the MEICA and Civils framework awards. The agreements are both for a period of four years with the option to extend for additional four years.

The water company will work with the following partners who have been appointed to deliver the infrastructure frameworks:

Infrastructure Networks:

  • Galliford Try Infrastructure
  • Morrison Utility Services
  • Mott MacDonald Bentley
  • nmcn
  • Peter Duffy
  • Sapphire Utility Services

Customer Focused Infrastructure:

  • Fastflow Pipeline Services
  • Morrison Utility Services
  • O'Connor Utilities
  • Peter Duffy Limited
  • Sapphire Utility Services L
  • Network Plus (formerly T&K Gallagher)

Crossrail bosses "very confident" line will open in 2021

A delayed London rail link, originally due to open last year, will start running in 2021, project bosses confirmed today.

Crossrail chiefs said the railway could still open in the first three months of the year, in line with revised predictions.

A new opening timetable will be announced in early 2020 – but project leaders today said they were “very confident” the line will open within 2021.

They also confirmed that costs will not increase further because of delays.

Crossrail is currently Europe’s largest infrastructure project, jointly funded by Transport for London and the Department for Transport (DfT).

Once complete, the new line will link Reading, Heathrow, and Essex to central London, with a branch to the south east of the city.

It was originally due to open in December 2018 and cost £14.8 billion – but the scheme has faced ongoing delays and escalating costs.This year, new leadership took over the project, with Tony Meggs appointed chair in January.

But Mr Meggs announced last month that the rail link would face yet more delays, and not open in late 2020, as he had originally hoped.

He also admitted project costs would increase by as much as £650 million, taking the total spend to over £18 billion.

This is on top of up to £750 million of lost ticket sale revenue caused by the delays.

But speaking at the London Assembly’s transport committee today, Mr Meggs said he was “very confident” that the line would open in 2021.

The chairman said Crossrail had been in “severe disarray” when he took over and his team had “since done a great deal” to improve its performance.

But he said more time was needed to develop software, and to test run trains on the line.

Mr Meggs said Crossrail “do not plan to ask for more money” as a result of further delays.

Project leaders are currently discussing funding with the DfT, to cover the £650 million cost gap, and projected revenue loss announced earlier.

The Mayor of London, Sadiq Khan, told the meeting he was confident that a new funding settlement will be agreed.

He said: “The relationship is a very good one – we are joint sponsors.

“The Crossrail board has the same candour with them [the DfT] that they have with us.

“I’m optimistic that we’ll reach a negotiation with the DfT that suits everyone”

He added: “Of course I share the frustration of Londoners that the Elizabeth line has not yet opened, and I apologise for this.

“But progress is being made, and we’ve already reached some very significant milestones in the last six months.”

Labour assembly member Navin Shah said the cost increases on the project had been “staggering”.

He said: “I’m somewhat reassured that the additional cost indication that you’ve made covers the overrun and the additional period required for completion.

“But I’m afraid we’ve heard this before in this chamber and again we have a situation where the cost has escalated.”

He added: “My worry is, could we be sitting round next year and looking at further cost increases on the project.”

Eurovia trials robo-cars to ferry tools to highways sites

Roads maintenance specialist Eurovia has struck a deal with a self-driving car developer to trial delivery of small plant, tools and materials to highways sites.

Kar-go autonomous delivery vehicle

The driverless electric delivery vehicles will also survey the road surface as they go feeding data into a central system to map the conditions of highways.

Surrey-based Academy of Robotics has developed Kar-go, which is Europe’s first road-based autonomous delivery vehicle.

Originally developed to dramatically reduce both the financial and environmental costs of last-mile parcel delivery, Eurovia UK recognised its potential for use in infrastructure and urban development work.

Kar-go’s operating system is able to understand the difference between features such as cracks, puddles, potholes and shadows.

Eurovia UK will in turn help Academy of Robotics to scale its training of autonomous vehicles by giving it access to digital camera data gathered by Eurovia’s fleet, which covers over 50,000 kms of roads.

Scott Wardrop, Chief Executive of Eurovia UK said: We have reviewed a number of autonomous vehicle solutions, but a critical component for us in developing this partnership was the technology’s ability to manage the complexity of recognising different road surfaces and their absolute commitment to sustainable innovation.”

William Sachiti, CEO and Co-Founder of Academy of Robotics said: “To date, most autonomous vehicle training and testing has taken place on well-marked roads or specially designated test centres, but these areas rarely reflect real-world conditions.

“This partnership and the access to the vast dataset of different road conditions it provides, together with the increased investment we have coming from our latest funding round will ensure we can test and train our technology on UK roads at an unparalleled scale and pace,” added Sachiti.

Southern Water sticks with Costain and MWH for AMP7

Southern Water has re-signed Costain and its existing joint venture partner MWH Treatment for its AMP7 investment programme.

Pending final determination of Southern Water’s ‘Water for Life’ Business Plan, this initial contract is expected to be worth £325m to the joint venture in an equal share over the five-year period.

Under the extended contract from AMP6, the joint venture will bring together its consultancy, design, digital, construction and commissioning skills to maintain and improve Southern Water’s water supply and wastewater treatment.

The AMP 7 contract will begin in April 2020 and will see Costain collaborating with Southern Water ensuring they optimise innovation and efficiency throughout AMP7 delivery. 

Alex Vaughan, chief executive officer of Costain, said: “Having now worked with Southern Water through the previous four regulatory AMP cycles, this contract extension is further testimony to the value of our long-term, strategic relationship.”

Neil Colman, director of engineering and construction, Southern Water said: “We fully expect the delivery of our PR19 programme to be challenging and require large efficiency gains.

“Only with partners as committed as we are to delivering smart solutions can we be sure of securing a resilient water future for the South East.”

Voice activated hard hats coming to sites

 

Alexa-style voice activated technology is being developed for use in hard hats.

Construction workers will be able to speak commands like “show me building plans” which will prompt designs to be projected onto a helmet visor.

The voice-activated technology beams real-time audio instructions into an earpiece and augmented reality (AR) graphics onto the visor.

The system is being developed at the University of the West of England (UWE Bristol) using artificial intelligence.

Scientists hope the system will remove the need for walkie-talkies or consulting hard copies of blueprints.

The conversational AI technology is being developed alongside construction firms including Costain, Winvic, TerOpta, Enable My Team, and Geo Green Power.

Professor Lukumon Oyedele, who is Assistant Vice-Chancellor for Digital Innovation and Enterprise at UWE Bristol, said: “Until now, conversational AI has mostly been used in labs and controlled settings.

“Here we are bringing it into a construction environment, where workers are using their hands and need a quick and effective way to gather information.

“One of the many challenges is to ensure that the instructions are audible and stand out, given that there is a lot of background noise on a busy construction site.

“We are therefore looking at technologies including noise-cancellation to allow for this.”

The system will also provide information for project managers, who will be able to access co-workers’ timesheets and know where they are located on site at any given time, as well as the status of various elements of the project.

Professor Oyedele said: “We hope that this technology will augment workers’ capabilities, to make construction more efficient. It is about improving worker’s productivity, ensuring a faster delivery process and getting it right the first time by avoiding defects.”

Tim Reeve, Technical Director at Winvic said: “It’s a real honour to be working with Professor Oyedele on his research project. AI can have relevant applications in unexpected places, and Winvic is eager to test the voice-activated headset that our data is helping to create.

“As our main focus is meeting clients’ needs – from a practical delivery point of view and also commercially – it was a natural progression for Winvic to become an early adopter of state-of-the-art BIM technology and we remain committed to digitally transforming construction.”

 

Build to rent investor plans first two London projects

The first development sites for the firm in London are an 80-flat development site at Beam Park in Dagenham and a 77-flat development site at Fresh Wharf, a major riverside scheme close to Barking town centre.

Sigma will work with Countryside Properties and L&Q New Homes at the Beam Park scheme and with Countryside Properties and Notting Hill Developments at Fresh Wharf.

The combined development cost of the two sites is £44m.

Fresh Wharf is expected to be completed towards the end of next year, with Beam Park completing by Spring 2021.

The new homes will be marketed and let under the investor’s ‘Simple Life’ letting brand.

Ian Sutcliffe, group chief executive at Countryside Properties, said :”We are delighted to be extending our very successful partnership with Sigma Capital into the London market.

“We have delivered over 4,000 private rented homes over the past five years together as part of differentiated mixed tenure approach to regeneration sites. We anticipate continuing growth from our relationship with Sigma in London and beyond.”

Sigma’s move into London follows its recent launch in Scotland, where it has entered into a collaboration agreement with house builder Springfield Properties and is targeting the delivery of hundreds of new rental homes across Scotland’s major cities, including Dundee, Edinburgh, and Glasgow.

Outside London, Sigma has delivered more than 3,000 new rental homes across the regions, through its PRS property platform.

Antobiotics in our rivers

The amount of antibiotics entering the River Thames would need to be cut by as much as 80 per cent to avoid the development and spread of antibiotic-resistant ‘superbugs’, a new study has shown.

Scientists from the Centre for Ecology & Hydrology (CEH) modelled the effects of antibiotic prescriptions on the development of antibiotic-resistant bacteria in a river. It found that across three-quarters of the River Thames catchment, the antibiotics present, due to effluent discharge, were likely to be at levels high enough for antibiotic-resistant bacteria to develop.

The study comes after England’s chief medical officer Professor Dame Sally Davies warned last week that bugs resistant to antibiotics could pose a more immediate risk to humanity than climate change, and may kill at least 10 million people a year across the world.

Dr Andrew Singer of the Centre for Ecology & Hydrology, who led the study, says: “Rivers are a ‘reservoir’ for antibiotic-resistant bacteria which can quickly spread to people via water, soil, air, food and animals. Our beaches offer a similar risk. It has been shown that surfers are four times more likely to carry drug-resistant bacteria than non-surfers.”

How antibiotics get into our rivers

Up to 90% of prescribed antibiotics taken by people pass through the body and into the sewerage system, where about half end up in rivers when effluent is discharged.

Dr Singer explains: “The release of drugs and bugs into our rivers increases the likelihood of antibiotic-resistant genes being shared, either through mutation or ‘bacterial sex’. This is the first step towards the development of superbugs as the drugs used to fight them will no longer work. Environmental pollution from drugs and bugs is a serious problem that we need to find solutions to.”

The CEH-led research was based on prescription data from clinical commissioning groups for two classes of antibiotics that biodegrade slowly. Macrolides, such as erythromycin and azithromycin, are used to treat a range of respiratory and sexually transmitted infections such as pneumonia, whooping cough and chlamydia. Fluoroquinolones such as ciprofloxacin, levofloxacin and moxifloxacin treat respiratory and urinary tract infections. 

Possible solutions

There are a number of different ways we could reduce the amount of antibiotics entering rivers, including:

  • reducing inappropriate prescriptions, either because the antibiotics will not reduce the infection, or the course of treatment is longer than is medically necessary
  • preventative action so fewer medicines are needed in the first place, such as more rapid diagnosis of medical conditions, greater uptake of vaccinations for illnesses and better hygiene controls in hospitals.
  • increased investment in research and development of new wastewater treatment processes that would remove the drugs and bugs from sewage.

There was a 6.1 per cent reduction in total antibiotic consumption in primary and secondary care in England between 2014 and 2018. However, antibiotics prescriptions per person in the UK per person is still higher than several European countries and double that of the Netherlands, where their controls on prescribing antibiotics and effective hygiene measures in the healthcare system have resulted in relatively low rates of antibiotic resistance.

The study, which also involved Royal Holloway, University of London, and received funding from UKRI, has been published in the journal PLOS ONE.

Further information

Andrew C. Singer, Qiuying Xu, Virginie D.J. Keller. 2019. Translating antibiotic prescribing into antibiotic resistance in the environment: a hazard characterisation case study. PLOS ONE. DOI: 10.1371/journal.pone.0221568

Contact us

01959 562572
recruit@alexander-assoc.co.uk

4 The Old Yard
Rectory Lane
Brasted
Westerham ,Kent
TN16 1JP

 

Office 2.15,
27 Clements Lane,
EC4N 7AE

We use cookies to provide you with the best possible browsing experience on our website. You can find out more below.
Cookies are small text files that can be used by websites to make a user's experience more efficient. The law states that we can store cookies on your device if they are strictly necessary for the operation of this site. For all other types of cookies we need your permission. This site uses different types of cookies. Some cookies are placed by third party services that appear on our pages.
+Necessary
Necessary cookies help make a website usable by enabling basic functions like page navigation and access to secure areas of the website. The website cannot function properly without these cookies.
ResolutionUsed to ensure the correct version of the site is displayed to your device.
essential
SessionUsed to track your user session on our website.
essential

More Details